You are the only operator at your plant, your background is SBR, and one morning a dissolved air flotation unit — a DAF — becomes your responsibility. No operating manual on the shelf. No list of spare parts. No record of what chemical dose the supplier actually tested. Nobody left to ask.
That is what one operator described in a public wastewater forum in early 2024: newly started, the sole operator on site, asking where the DAF operating standards and learning material even are. If you are buying a DAF, or about to accept one, that post is your warning. The machine is only half the purchase. The other half is the handover — the documents, training, and acceptance records that let someone run it after the supplier’s truck leaves. This checklist tells you what to demand, in writing, before you sign acceptance and release final payment.
Why the Handover Decides Whether the DAF Works for You
A DAF arrives as a package quoted against your water data. The supplier knows what it assumed about your flow, your solids, and your chemistry. If none of that knowledge is handed over, it leaves with the installation crew, and you pay for it next: in weeks of guessing, in chemical wasted on trial and error, in a warranty claim answered with “that was never in the scope.” Before acceptance, the supplier still wants your signature and final payment; after acceptance, you are asking for favours. Make every item below a contract deliverable, agreed before you pay the deposit.
The Eight Things to Demand Before You Sign
1. The operating manual and the SOP set — for your unit, not a generic catalogue
Demand a manual written for the unit as built — exact model, configuration, and control panel on your floor. A generic catalogue manual covering five models is not a handover document. Demand the standard operating procedures as separate, short documents too — start-up, normal operation, shutdown, and the daily and weekly checks — written so a competent operator with no DAF background can follow them. If the manual is only in the supplier’s language, agree the translation before ordering, not after delivery.
2. As-built drawings and the equipment datasheets
Demand the as-built general arrangement, piping and instrumentation, and electrical drawings — marked as built, not as proposed. Demand the datasheet of every major bought-in item as well: pumps, blowers or compressors, valves, instruments, and the control system. When a pump fails in two years, the datasheet lets your maintenance team order the right replacement in a day instead of measuring the old one and guessing.
3. The chemical dosing-window documentation
What you need at handover is a document, not a lesson in chemistry: the dosing window the supplier validated for your application, with the jar-test or trial records behind it. Demand it in writing — which chemicals, the dose range tested, the order of addition, and the water conditions behind those doses. If the supplier cannot produce the test records, the dose was never validated for your water — do not accept the unit as proven against your effluent. A single dose number with no range and no basis tells the next operator nothing when the incoming water changes.
4. The wear-parts and spares list — with part numbers and lead times
Seals, scrapers, nozzles, and consumables in the air and chemical systems all wear. Demand a spares list naming each wear part, with the supplier’s part number, the recommended first-year stock quantity, and the lead time for each item. Then demand the first set of critical spares with the delivery, or a written price and delivery time. Without lead times it is a shopping list, not a plan — the part that takes eight weeks is the one you needed last week. See also our general guide: Can you provide spare parts for the water treatment machineries.
5. Training — delivered, and recorded
Demand training as a named deliverable: who is trained, on what, for how long, and what record proves it. A two-hour talk on delivery day, with no notes and no attendance record, evaporates the moment the trainer leaves. Ask for a training plan in the contract — classroom time on the manual and SOPs, hands-on time on the running unit, and a signed record per operator listing the topics covered. For a one-operator plant, that record is the only proof the next hire has that anyone was trained.
6. The acceptance test and its documents
Demand a written acceptance test, agreed before delivery, stating what will be measured, under what water conditions, and what counts as a pass. Run it on your water, at the quoted flow, with results recorded and signed by both sides. Just as important is the document behind the test: the quotation data sheet the system was sized on, so you can check line by line that the unit delivered matches the unit quoted. Our technical sister site explains what it should contain: Specifying a DAF: the RFQ data sheet for comparable quotes. If the test is waived or run on clean water, say so in writing — and do not sign an acceptance claiming a performance nobody measured.
7. Warranty terms in writing — with the conditions spelled out
Demand the warranty in writing, not as a line in an email: coverage, duration, what voids it, and who pays freight on a warranty part. Watch the conditions — many warranties require the manual to be followed and the recommended spares used, which is why items 1 and 4 matter. A warranty you cannot comply with is not a warranty. Our guide to the commercial terms is here: Payment Terms, Warranty and Inspection: What to Put in Your Equipment Order.
8. The sludge and downstream note
The solids a DAF removes go somewhere. Demand a written note stating the expected float and sludge stream: where it leaves the unit, what handling it needs, and what the supplier assumed about its disposal. This is the item buyers forget, and the one that creates the next purchase. If the float is oily or high in solids, your dewatering step must handle it — see our buyer-side article: Stop Washing Your Filter Belts: Dewatering Oily DAF Sludge with Volute Presses. If you are still planning the sludge step, send your sludge numbers first — our screw press guide shows which four: Quoting a Screw Press? Send These 4 Sludge Numbers First.
The Handover Checklist at a Glance
| # | Demand before acceptance | What “good” looks like |
|---|---|---|
| 1 | Operating manual + SOP set | Written for your unit as built, in your language |
| 2 | As-built drawings + equipment datasheets | Marked as built, with every major item’s datasheet |
| 3 | Chemical dosing-window documentation | Dose range with jar-test or trial records behind it |
| 4 | Wear-parts and spares list | Part numbers, first-year stock, lead time per item |
| 5 | Training plan and signed records | Named operators, topics covered, signed on the day |
| 6 | Acceptance test + quotation data sheet | Run on your water, results recorded and signed |
| 7 | Warranty terms in writing | Coverage, duration, conditions, freight responsibility |
| 8 | Sludge and downstream note | Where float leaves, what handling it needs |
How to Use This Checklist When You Order
Put the eight items in your purchase order as deliverables, with a delivery date for the documents and a holdback on final payment until they arrive. A common structure: deposit on order, payment on delivery, final payment only after documents, training, and acceptance test. Documents are part of the delivery, and they are paid for like the steel. If your DAF is already installed and the documents never arrived, use the same list to recover them — ask for each item in writing, keep the replies with the plant records, and record what cannot be recovered as a gap. The next operator deserves to know what is missing.
What to Send HNS for a Quotation
A DAF quotation from HNS starts with the same discipline: your water data, your flow, and what the treated water must meet. Send your average and peak flow, the solids and oil content of the incoming water, the discharge standard, and any space or installation limits. We will confirm anything missing before quoting, and the quotation will state the data it was based on, so the handover file can be checked against it. Our DAF systems are manufactured at our own factory in Yixing, and the handover documents above are part of the delivery we agree in the order. We do not do whole-plant process design, civil works, commissioning, or operation: we supply the equipment package and its documentation, and your plant team runs it.
The Point of the Checklist
The operator in that forum post was not asking for a favour — he was asking for the half of the purchase that should have arrived with the machine. Demand the eight documents before you sign and hold the final payment until they are in your hands. A DAF with a complete handover file is an asset your next operator can run. A DAF without one is a machine only its installer understands, and installers leave.