Ask three suppliers for a tube settler price and you will often get three numbers that are 30 to 40 percent apart — and none of them will be comparable. The usual reason is not that one supplier is dishonest. It is that each of them filled in the blanks you left in your enquiry with different assumptions: a different module size, a different sheet thickness, a different idea of whether support frames are included, and a different guess about your water.
A tube settler is a pack of inclined tubes or hexagonal channels that sits in a clarifier basin and gives suspended solids a short distance to settle. The buyer who sends complete data gets a quotation that can be checked line by line. The buyer who sends only a tank size gets a price that cannot be checked at all — and discovers the missing items only when the shipment arrives.
This article is the checklist version of that lesson. It covers what a proper tube settler quotation should contain, the six pieces of data your supplier needs before they can price it, and how to compare two quotations without comparing a complete scope against an empty one.
What a Tube Settler Quotation Should Contain
Before you judge a price, check what it covers. A complete tube settler quotation states, in writing:
- The modules themselves — quantity, module dimensions, channel size and shape, sheet material (PP or PVC), and sheet thickness.
- Support frames and fixings — whether the steel or FRP frame, brackets, bolts and spacers are included, or whether you are expected to fabricate them locally.
- Packing and freight terms — how the modules are packed for export, and whether the price is ex-works, FOB, or CIF to your port.
- Documentation — installation drawings, a layout showing how the modules sit in your basin, and a material certificate if one was agreed.
If any of those four items is missing from the quotation, the price is not a price. It is a starting figure with the expensive parts still to come. The most common surprise is the support frame: modules are light and cheap to ship, frames are not, and a buyer who assumed they were included can face a second bill nearly as large as the first.
Ask the supplier to confirm in the quotation whether the scope is “modules only” or “modules plus frames, fixings and installation supervision.” That one sentence removes most of the ambiguity from the comparison that follows.
The Six Data Points Your Supplier Needs
1. Design flow — average and peak
State the flow the settler must handle in cubic metres per hour, and state both the average and the peak. A settler sized for the average flow will be overloaded every time the peak arrives, and the supplier who only hears the average will quote a smaller, cheaper package that fails on the busiest day.
If your flow varies by season or by production shift, say so. The supplier does not need your full process design — that remains your engineer’s work — but they do need the flow range the equipment must live with.
2. Influent solids — what the settler must remove
Give the suspended solids concentration coming into the basin, and say what kind of solids they are: biological floc from an activated sludge or MBBR plant, chemical floc after dosing, sand and grit, or oily solids from a food or industrial stream. Tube settlers handle light, settleable floc well. They are not a screen, and they are not a filter. A supplier who knows the solids type will tell you honestly whether tube settlers are the right tool; a supplier who is never told will simply quote the modules.
If you have a target for the clarified effluent — for example, a solids limit set by the next treatment step or by a discharge permit — include it. It tells the supplier what performance the quotation is being judged against.
3. Basin dimensions — length, width and water depth
Send the internal dimensions of the basin the modules will sit in: length, width, and water depth, plus a sketch or drawing if one exists. Two things depend on these numbers. First, the module footprint: the supplier must cut or combine modules to fit your basin without leaving dead corners where water short-circuits around the pack. Second, the support frame: the frame is designed around your basin, not around a standard catalogue size.
If the basin is an existing one being retrofitted, say so, and include photographs of the basin, the existing launders or weirs, and any obstructions such as walkways, pipes or mixers. A retrofit quotation written without that information is a guess. For the design-side detail of a retrofit — how module depth and layout interact with the existing basin — our technical site covers the design data separately.
4. Water temperature and chemistry
State the water temperature range and anything unusual about the chemistry: high temperature, high pH, strong solvents, oil and grease, or seawater. The reason is material selection. PP and PVC do not behave identically in hot or aggressive water, and a module quoted in the wrong material is a module that will warp or embrittle in service.
You do not need to supply a full laboratory analysis. Temperature range, pH range, and a note of any aggressive chemicals or oil in the stream is enough for the supplier to confirm the material in writing — and to warn you if the standard material is not suitable.
5. Material, sheet thickness and module format
If your specification calls for a particular material or sheet thickness, state it. If it does not, ask the supplier to state what they are offering and why. The questions worth asking in writing are:
- PP or PVC, and what governs the choice for your water?
- Sheet thickness, in millimetres, as supplied — not as a catalogue nominal value.
- Module format — inclined tube or hexagonal channel — and the channel size.
- Whether the modules are supplied loose, pre-assembled into blocks, or glued into packs.
None of these details is cosmetic. Thinner sheet costs less and is easier to damage in handling; pre-assembled blocks cost more and install faster. A quotation that states all four can be compared with another that states all four. A quotation that states none of them cannot be compared with anything.
6. Scope — supply only, or supply plus installation
Finally, state what you want the supplier to do beyond shipping the goods. Options range from modules only, to modules plus frames, to a supervised installation with a technician on site. Each step adds cost and removes risk. There is no right answer, but there is a wrong one: leaving the scope unstated and discovering at the port that nobody owns the installation.
How to Compare Two Tube Settler Quotations
Once you have two complete quotations, the comparison is a table, not an argument. Check these six lines in each one:
| Check | What to look for |
|---|---|
| Module quantity and footprint | Enough coverage for your basin, no unexplained gaps |
| Material and sheet thickness | Stated in writing, matched to your water |
| Support frames and fixings | Included, or priced separately and clearly |
| Installation drawings | Layout for your basin, not a generic catalogue drawing |
| Packing and freight terms | Export packing stated, Incoterms stated |
| Documentation | Material certificate and installation guide included |
If one quotation is much cheaper, the difference is almost always in one of those six lines — thinner sheet, no frames, no drawings, or a smaller module area. Find the line before you sign, not after the container arrives.
What to Send HNS for a Quotation
Send us the six items above and we will return a written quotation on the same basis: design flow (average and peak), influent solids and type, basin dimensions with a sketch or photos, water temperature and chemistry, your material preference if you have one, and the scope you want — modules only, or modules plus frames and supervision.
Tube settlers are manufactured at HNS’s own factory in Yixing, alongside our MBBR media, sponge media and clarifier equipment, so the quotation you receive states the material, sheet thickness and module format as manufactured — not as a trader’s catalogue line. We supply media and equipment packages; whole-plant process design, civil works, commissioning and operation remain outside our scope, and your process engineer stays in charge of those decisions.
If you are planning a wider upgrade, tube settlers are frequently ordered alongside an MBBR retrofit or a clarifier upgrade — mention the whole project in the enquiry so the two scopes do not contradict each other.
The Short Version
A comparable tube settler quotation needs six things from you: flow, solids, basin dimensions, water chemistry, material preference, and scope. Send those six, require the supplier to answer in writing on the same six, and the cheapest quote will usually stop looking cheap — because it was never the same scope. Send the six to HNS and we will quote on exactly that basis.
Contact HNS for a tube settler quotation — include the six data points above and we will reply with a written quotation you can compare line by line.